Thursday, October 9, 2008
Host Missionary Website
http://www.thevenezuelareport.com/
Team Update
1 – Multi-Purpose Building
Finished welding and screwing in the metal panels
Starting to install the windows.
Pouring cement for two patios tomorrow.
Poured cement 2nd floor
Poured cement for the landing for the stairs
Any extra cement will be used for some roads in the compound
2 – Apartment
Laying out metal walls.
Electrical done
Putting up drywall
3 – Sidewalk
DONE WITH IT – What it took them 8 months to do on the other side, took our Team 2 days to do!
4 – Orphan Homes
Exterior of the first two houses done
Primed exterior of third house today
Then start interiors
5 – Chicken Tabernacle (Okay, really a chicken barn, but they are having fun calling it this!)
Roof was completed
Chickens are expensive in Venezuela and this represents an investment/income for them.
Saturday, October 4, 2008
Friday, October 3, 2008
Venezuela 2008


The building that we will be working on is a multipurpose building for the orphange and a church. This is the church that the youth of JRA helped start. It is a prefab metal building and will be a church, offices, classrooms, medical clinic for the community, and 2 apartments for workers from the states who come.
Only the frame is up for now. The team will pour the floor for the second story, possibly put in windows and doors, and pour some porches on it. Other projects at the same site will include sidewalks, sheet rock, electricity, etc.
Prayer Requests: Health and safety for the team and the missionary, souls to be saved, and house parents for the orphanage.